Washington Square Sub Storm Water Improvements

The Washington Square Subdivision - Storm Water Management Improvements project included the installation of approximately 1,000 linear feet of concrete (RCP) storm sewer, the installation of 5 storm sewer structures, and enhancements to the detention basin. The existing storm sewer that served as the outlet for the detention basin was corrugated metal pipe that failed. This failure caused the detention basin to not function properly.  

Washington Square Improvements photo 2The detention basin enhancements allowed for positive drainage from the inlet to outlet and increased storage capacity, which will reduce flooding in the streets of the subdivision.